Skip To Main Content

Facilities

The Glen Cove City School District operates six school buildings and two administrative buildings spread across approximately 100 acres in the City of Glen Cove. The facilities are managed and maintained by the District’s Buildings & Grounds (B&G) Department.  

The District will update the site with information as it continues to upgrade and renovate facilities in our district. Please check back for updates and new information. 

Construction Updates

Energy Performance Contract (EPC) Progress Report 4-5-2024

Construction Update 11-22-24

Glen Cove City School District Capital Projects

Renovations and upgrades are performed in several manners: as Capital Projects and Maintenance Projects.
Capital Projects are larger in cost and scope of work.

Proposed Timeline for District Facilities Upgrades
updated October 2024

Completed Capital Projects

Maintenance Projects are conducted over time by our employees within the district. 

Completed Maintenance Projects

 

Construction Update Photos

November 2024  Underground utilities have been relocated. Excavation has commenced. Footings and foundation construction to begin week of November 25th. 

November 2024

Underground utilities have been relocated. Excavation has commenced. Footings and foundation construction to begin week of November 25th. 

November 2024  Landing Elementary School Classroom Addition  Curtain wall nearing completion. Switchgear installation in progress. Classroom and bathroom framing completed. Drywall installation to commence. 

November 2024

Landing Elementary School Classroom Addition

Curtain wall nearing completion. Switchgear installation in progress. Classroom and bathroom framing completed. Drywall installation to commence. 

Districtwide Interior Door Replacement

November 2024

Districtwide Interior Door Replacement Complete

Door and signage replacement project completed

June 2024  Grand opening of newly constructed tennis courts

June 2024

Grand opening of newly constructed tennis courts

June 2024  Grand opening of newly constructed tennis courts

June 2024

Grand opening of newly constructed tennis courts

Grand opening of the Tennis Complex includes racquetball courts

June 2024

New racquetball courts 

June 2024  New basketball courts

June 2024

New basketball courts

Gribbin School solar panels

March 2024

Gribbin School

Installed solar arrays with a RM10 EVO footing style

Solar Installation at GCHS  Footings, panels, and ballast blocks have been installed on the lower gym roof.  These 150 panels will not be able to produce power until the inverter and AC-side equipment is installed and PSE&GLI gives their final approval.

March 2024

Solar Installation at Glen Cove High School

Footings, panels, and ballast blocks have been installed on the lower gym roof.

These 150 panels will not be able to produce power until the inverter and AC-side equipment is installed and PSE&GLI gives their final approval.

Connolly School  Completed all of the hallways in the building replacing 1x4’ surface mount fluorescent fixtures with recessed 2x4 LED flat panels

March 2024

Connolly School

Completed all of the hallways in the building replacing 1x4’ surface mount fluorescent fixtures with recessed 2x4 LED flat panels

Created a consistent lighting layout in the hallways with the new recessed panels

Replaced smoke alarms and integrated them into the new grid

March 2024  High School athletic field is completed.

March 2024

High School athletic field is completed.

Tennis Complex Under Construction

March 2024

Tennis Complex Under Construction

Landing School Construction

November 2023

Landing School's latest drone photos showcasing the underpinning progress. The transformation continues, with this essential work set to unfold throughout the coming week.

Landing School Construction

November 2023

Landing School's latest drone photos showcasing the underpinning progress. The transformation continues, with this essential work set to unfold throughout the coming week.

Landing School Construction

November 2023

Landing School Construction

High School Tennis Courts - under construction in November 2023

November 2023

The latest drone shots capture the final stages of fine gravel installation on the football/track and tennis courts. Exciting progress as LandTek receives a partial delivery of Turf material onsite. 

High School Tennis Courts

November 2023

The latest drone shots capture the final stages of fine gravel installation on the football/track and tennis courts. Exciting progress as LandTek receives a partial delivery of Turf material onsite. 

March 2024  Interior Doors

March 2024

Interior Doors

March 2024  Deasy School Construction of Elevator

March 2024

Deasy School Construction of Elevator

High School Athletic Fields

November 2023

The latest drone shots capture the final stages of fine gravel installation on the football/track and tennis courts. Exciting progress as LandTek receives a partial delivery of Turf material onsite. 

High School Athletic Fields

November 2023

The latest drone shots capture the final stages of fine gravel installation on the football/track and tennis courts. Exciting progress as LandTek receives a partial delivery of Turf material onsite. 

October 2023  High School Athletic Fields Under Construction

October 2023

High School Athletic Fields Under Construction

October 2023  ​​​​​​​High School Athletic Fields Under Construction

October 2023

High School Athletic Fields Under Construction

October 2023  High School Athletic Fields Under Construction

October 2023

High School Athletic Fields Under Construction

October 2023  Construction of Athletic Fields

October 2023

Construction of Athletic Fields

Tennis Court Area 10-23-2023

October 2023

Tennis Court Area

October 2023  Tennis Court Area - Beginning Stage of Construction

October 2023

Tennis Court Area - Beginning Stage of Construction

September 2023  High School Athletic Fields Under Construction

September 2023

High School Athletic Fields Under Construction

September 2023  High School Tennis Complex Beginning Phase of Construction

September 2023

High School Tennis Complex Beginning Phase of Construction

Deasy School Elevator Addition Construction Photos  Ongoing construction efforts for the elevator addition project. The focus is on relocating drain pools and shifting drain lines to make way for the new addition.

September 2023

Deasy School Elevator Addition Construction Photos

Ongoing construction efforts for the elevator addition project. The focus is on relocating drain pools and shifting drain lines to make way for the new addition.

Deasy School Elevator Addition Construction Photos

September 2023

Deasy School Elevator Addition Construction Photos

Ongoing construction efforts for the elevator addition project. The focus is on relocating drain pools and shifting drain lines to make way for the new addition.

Deasy School Elevator Addition Construction Photos

September 2023

Deasy School Elevator Addition Construction Photos

Ongoing construction efforts for the elevator addition project. The focus is on relocating drain pools and shifting drain lines to make way for the new addition.

September 2023  Deasy School Elevator Addition Construction Photos  Ongoing construction efforts for the elevator addition project. The focus is on relocating drain pools and shifting drain lines to make way for the new addition.

September 2023

Deasy School Elevator Addition Construction Photos

Ongoing construction efforts for the elevator addition project. The focus is on relocating drain pools and shifting drain lines to make way for the new addition.

 

COMMUNITY USE OF SCHOOL FACILITIES

It shall be the policy of the Board to encourage the greatest possible use of school buildings for community-wide activities. This is meant to include use by recognized civic, social and fraternal and religious organizations in accordance with law. Groups wishing to use the school facilities must secure written permission from the Superintendent and abide by the rules and regulations established for such use, including restrictions on alcohol, tobacco and drug use. The Superintendent, at his/her discretion, may consult with the Board of Education. Monthly reports may be made to the Board regarding community use of the school facilities.


Any questions, please email Buildingsandgrounds@glencoveschools.org