Facilities
The District will update the site with information as it continues to upgrade and renovate facilities in our district. Please check back for updates and new information.
Construction Updates
Energy Performance Contract (EPC) Progress Report 4-5-2024
Construction Update March 14, 2025
Glen Cove City School District Capital Projects
Renovations and upgrades are performed in several manners: as Capital Projects and Maintenance Projects.
Capital Projects are larger in cost and scope of work.
Proposed Timeline for District Facilities Upgrades
updated October 2024
Maintenance Projects are conducted over time by our employees within the district.
Completed Maintenance Projects
Construction Update Photos
March 2025
Deasy Elementary School Elevator and Staircase
In the process of obtaining the Certificate of Occupancy
March 2025
Landing Elementary Classroom Addition
Curtain wall completed. Switchgear installation completed and energized. All drywall completed and painted. Bathroom fixtures being installed. Flooring installation to commence March 24, 2025.
March 2025
Deasy School Classroom Addition
The steel structure has been erected. Mechanical, electrical, and plumbing rough-in has commenced, with concrete slab pouring scheduled. Masonry work is set to begin shortly.
High School Science Lab, Cafeteria, Bathroom Reconstruction Summer 2025
Mechanical and plumbing work has commenced. Classroom casework is in production. Steel bracing installed for air
conditioning units.
November 2024
Deasy Classroom Addition
Underground utilities have been relocated. Excavation has commenced. Footings and foundation construction to begin week of November 25th.
November 2024
Landing Elementary School Classroom Addition
Curtain wall nearing completion. Switchgear installation in progress. Classroom and bathroom framing completed. Drywall installation to commence.
November 2024
Districtwide Interior Door Replacement Complete
Door and signage replacement project completed
June 2024
Grand opening of newly constructed tennis courts
June 2024
Grand opening of newly constructed tennis courts
June 2024
New racquetball courts
June 2024
New basketball courts
March 2024
Gribbin School
Installed solar arrays with a RM10 EVO footing style
March 2024
Solar Installation at Glen Cove High School
Footings, panels, and ballast blocks have been installed on the lower gym roof.
These 150 panels will not be able to produce power until the inverter and AC-side equipment is installed and PSE&GLI gives their final approval.
March 2024
Connolly School
Completed all of the hallways in the building replacing 1x4’ surface mount fluorescent fixtures with recessed 2x4 LED flat panels
Created a consistent lighting layout in the hallways with the new recessed panels
Replaced smoke alarms and integrated them into the new grid
March 2024
High School athletic field is completed.
March 2024
Tennis Complex Under Construction
November 2023
Landing School's latest drone photos showcasing the underpinning progress. The transformation continues, with this essential work set to unfold throughout the coming week.
November 2023
Landing School's latest drone photos showcasing the underpinning progress. The transformation continues, with this essential work set to unfold throughout the coming week.
November 2023
Landing School Construction
November 2023
The latest drone shots capture the final stages of fine gravel installation on the football/track and tennis courts. Exciting progress as LandTek receives a partial delivery of Turf material onsite.
November 2023
The latest drone shots capture the final stages of fine gravel installation on the football/track and tennis courts. Exciting progress as LandTek receives a partial delivery of Turf material onsite.
March 2024
Interior Doors
March 2024
Deasy School Construction of Elevator
November 2023
The latest drone shots capture the final stages of fine gravel installation on the football/track and tennis courts. Exciting progress as LandTek receives a partial delivery of Turf material onsite.
November 2023
The latest drone shots capture the final stages of fine gravel installation on the football/track and tennis courts. Exciting progress as LandTek receives a partial delivery of Turf material onsite.
October 2023
High School Athletic Fields Under Construction
October 2023
High School Athletic Fields Under Construction
October 2023
High School Athletic Fields Under Construction
October 2023
Construction of Athletic Fields
October 2023
Tennis Court Area
October 2023
Tennis Court Area - Beginning Stage of Construction
September 2023
High School Athletic Fields Under Construction
September 2023
High School Tennis Complex Beginning Phase of Construction
September 2023
Deasy School Elevator Addition Construction Photos
Ongoing construction efforts for the elevator addition project. The focus is on relocating drain pools and shifting drain lines to make way for the new addition.
September 2023
Deasy School Elevator Addition Construction Photos
Ongoing construction efforts for the elevator addition project. The focus is on relocating drain pools and shifting drain lines to make way for the new addition.
September 2023
Deasy School Elevator Addition Construction Photos
Ongoing construction efforts for the elevator addition project. The focus is on relocating drain pools and shifting drain lines to make way for the new addition.
September 2023
Deasy School Elevator Addition Construction Photos
Ongoing construction efforts for the elevator addition project. The focus is on relocating drain pools and shifting drain lines to make way for the new addition.
COMMUNITY USE OF SCHOOL FACILITIES
It shall be the policy of the Board to encourage the greatest possible use of school buildings for community-wide activities. This is meant to include use by recognized civic, social and fraternal and religious organizations in accordance with law. Groups wishing to use the school facilities must secure written permission from the Superintendent and abide by the rules and regulations established for such use, including restrictions on alcohol, tobacco and drug use. The Superintendent, at his/her discretion, may consult with the Board of Education. Monthly reports may be made to the Board regarding community use of the school facilities.
- Please view the User Guide here.
- Register for a new account here (only needed for first time use).
- Log in here to view schedules and make a reservation.
Any questions, please email Buildingsandgrounds@glencoveschools.org
- The Complete Board Policy #3280
- Lead In Water Remediation Plan | 2016
- Lead in Drinking Water Sampling and Remediation Plan | 2020-2021
- Letter to Parents Water Testing | June 2021
- Letter to Parents Water Testing | April 2025
- Letter to Parents Water Testing Results 2023 - 2025 | April 2025
Contact
Daniel Novak
Director of Facilities
dnovak@glencoveschools.org
516-801-7090
Teresa Leotta
Administrative Assistant
tleotta@glencoveschools.org
516-801-7091